"A one stop solution provider for Erection, Testing, Commissioning, Operation & Maintenance of Substations and Transmission Lines"

Completed : Operation & Maintenance

Completed : Operation & Maintenance

M/s. Sterlite Power Grid Ventures Limited - 4 Years

- Jabalpur - Dharamjaygarh - 180 kms (Chhattisgarh portion)

M/s. Adani Infrastructure Management Services Limited - 5 Years

- Bikaner – Deedwana (Rajasthan) - 111 kms Deedwana – Ajmer (Rajasthan) - 129 kms

- Hinduan - Alwar (Rajasthan) - 96 kms


M/s. KEC Bikaner – Sikar Transmission Line - 1 Years

- Sikar - Bikaner - 172 kms


M/s. Power Mech Projects Ltd. - 3 Years

- Jhabua Power plant - Jabalpur (Madhya Pradesh) - 70 kms


M/s. Sterlite Power Grid Ventures Limited

- Bongaigaon (Assam) - Siliguri (West Bengal) - 222 kms - 5 Years

- Samba - Amargarh (Jammu & Kashmir) - 281 kms - 2 Years

- Uri - Wagoora (Jammu & Kashmir) - 7 kms - 2 Years


M/s. GMR Energy Ltd. - 4 Years

- Tilda - Durg (Chhattisgarh) - 65 kms


M/s. Kalpataru Power Transmission Ltd.

- Alipurduar - Siliguri (West Bengal) - 116 kms - 1 Year

- Kishanganj - Darbhanga (Bihar) - 205 kms - 1 Year

- Jharli - Kabulpur (Haryana) - 35 km - 8 Years

- Kabulpur - Dipalpur (Haryana) - 65 km - 8 Years

M/s. Isolux Corsan Ltd.

- 400/220/132 kV Substation at Gonda (Uttarpradesh) - 1.5 Years


M/s. Adani Infrastructure Management Services Limited

- 400/220/132 kV Substation at at Deedwana (Rajasthan) - 5 Years

- 400/220/132 kV Substation at at Alwar (Rajasthan) - 5 Years


M/s. Tehri Hydroelectric Development Corp. Ltd.

- Maintenance of 400 kV Sub Station at Koteshwar HEP - 7.5 Years


M/s. Techno Electric & Engineering Co. Ltd.

- 400/220/132 kV Substation at Kabulpur (Haryana) (Since February 2012)

- 400/220/132 kV Substation at Dipalpur (Haryana) (Since February 2012)


M/s. Kalpataru Power Transmission Ltd.

- 400 kV GIS Substation at Darbhanga (Bihar) - 1 Year

M/s. Adani Infrastructure Management Services Limited

- Sujangarh - Deedwana (Rajasthan) - 30 kms - 5 Year


M/s. Bhilai Steel Plant

- 220 kV (MSDS) Main Step-Down Substation- 15 kms - 2 Years

M/s. JSW Steel Ltd.

- 220/22 kV Substation at Pali Village Vasind Disst. Thane - 10 Years


M/s. Chhattisgarh State Electricity Board

- 220/132/33 kV Substations at 6 Different locations - 5 Years


M/s. Amby Valley

- 220/33 kV Substations at Amby Valley Pune - 5 Years


M/s. Gujarat Energy Transmission Corporation Ltd

- 220/66 kV Substations at 5 Different locations - 2 Years


M/s. Haryana Power Generation Company Ltd

- 220 kV Sub Stations at Panipat (Maintenance only) - 2 Years

- 220 kV Substation at Yamuna Nagar (Maintenance only) - 2 Years


M/s. Reliance Industries Limited

- 220/33 kV, Substation at Kharadpada (Silvassa) - 7 Years


M/s. M. P. Power Transmission Co. Ltd.

- Operation & Maintenance of 220 kV Substation at Channera - 2 Years

- Operation & Maintenance of 220 kV Substation at INDORE (Since October 2018)

M/s. Bhilai Steel Plant SAIL (Chhattisgarh)

- 132 kV MSDS (Main Step - Down Station) - 11 kms - 2 Years

M/s. Chhattisgarh State Power Trans. Co. Ltd.

- 132/33 kV - 10 Nos of Substations - 9 Years


M/s. RRCAT, Dept of Atomic Energy, Indore

- 132/11 kV Main Receiving Substation and 11/0.44 kV Indus - 6 Years


M/s. Rajasthan Rajya Vidyut Prasaran Nigam Limited

- 132 kV 6 Nos. of Substations at different locations of Alwar Circle (Jaipur) - 4 Years

- 132 kV 6 Nos. of Substations at different locations of Bhilwara Circle (Ajmer) - 4 Years


M/s. NTPC

- 11/132 kV - 01 No. of Solar Power Plant at Rajgarh (M.P.) - 2 Years


M/s. M. P. Power Transmission Co. Ltd.

- Operation & Maintenance of 132 kV Substation at Bhopal IT Park - 2 Years

M/s. GETCO

- 66/11 kV Substations at different locations in Gujarat M/s. GETCO - 90 Nos. for 7 Years & 91 Nos. - 3 Years

M/s. Chhattisgarh State Power Distribution Co. Ltd.

- 33/11 kV - 58 Nos. of Substations at different locations - 6 Years